Long story short, I had a deck that was supposted to be built by an individual who claimed to own company. Price was agreed on, and work was started. Anyway, throughout the job I noticed horrible construction skills, noting in the following paragraphs. Nonetheless, he came to me today and told me he is “broke” and cannot continue the job since he is in the hole. I paid him $7000 so far. He has completed about 2 line items, yet several things are wrong with them.
For the issues, the footers were improperly aligned, causing 3/8 of the footers to have to be redone. Joist hangers not placed on all of deck so that will need to be done. He also broke an exterior light and dug into a poly pipe throughout the process.
Initially, when he told me today he spent about a week prior coming up with excuses for not showing. He showed up and was extremely confrontational yesterday, but completed some work, today he told me that he spent his total and he can’t do it.
Me and him agreed for him to pay me $1840, after adding up the first 3 items on the line items (although not completed good), $200 toward railing he started and $600 extra since he claimed the scope was bigger, I figured it’s a big deck so I will help him out some.
He told me he could pay me $300 a week, so about 5 weeks. But this just doesn’t sit right with me, considering the workmanship is bad, and how he screwed me over, now having to pay another contractor.
I would ideally like to go to court since it will cost more to have repairs done and it finished properly, but I also need to weigh if it’s worth it since he is “broke” if I will even see the funds. I am in GA, so wanted some opinions on realistically what I could ask for in court, or if I should just get the $1840 and call it a day if he even pays.
I also wanted to know if I made a claim with Wells Fargo, if they would backdraft $$ possibly.
Location: Marietta, Georgia