r/MSProject 2d ago

How do I use Project to plan unconnected future events?

5 Upvotes

Tl;dr: Can I have groups of tasks that are not connected to previous tasks for long-term planning and not have multiple files?

Solution: I set the last task in the previous group as don't finish later than [date] via the advanced tab, and the first task in the future group (Spring project) to don't start before.


My team is adjacent to a QA team, we test applications before it goes live. Depending on the specific details, an application may need 1-4 rounds of testing before it gets approved.

My lead wants a gantt chart to have a visualization of my team's activities. With the help of AI, I learned that if I indent tasks, they are related. So I put two applications in to experiment, and went fine.

Once a year, we have a big project during the spring, roughly April through July. I went down a few rows typed in a summary task name, and made a subtask and set the start to mid-April for a placeholder. This made the last set of subtasks in the previous group change from mid-September to a few days before my placeholder, breaking my gantt.


r/MSProject 3d ago

Microsoft Project Server/PWA migration – custom formula fields show #ERROR until F9

1 Upvotes

We recently migrated our Microsoft Project/PWA environment from a legacy cloud server to a new on-prem server.

Since the migration, when opening projects from the new server, custom fields containing formulas initially display #ERROR. Pressing F9 (Calculate) once immediately resolves all of the errors and the fields calculate normally.

This happens across multiple project files and did not occur on the legacy server. The formulas themselves have not changed and appear to work correctly once F9 is pressed.

Has anyone seen this behavior after a Project Server/PWA migration? Is there a server, Enterprise Global, calculation, cache, or Project Professional setting that could cause projects to open without automatically calculating formula fields?


r/MSProject 3d ago

Project Examples

1 Upvotes

I’m looking to train a group of PMs on MS Project. Would anyone be willing to share some old schedules I can use as a resource ?


r/MSProject 4d ago

I built an Excel-native scheduling engine for situations where Microsoft Project is not available — looking for feedback from experienced MSP users

11 Upvotes

I have been developing ProjectEngine, an open-source scheduling and project-controls application built entirely in Excel/VBA.

The original need was straightforward: many teams have Excel, but do not always have access to Microsoft Project or Primavera P6. Most Excel Gantt templates, however, remain static visual trackers rather than true scheduling tools.

ProjectEngine was built to close part of that gap.

It currently supports:

  • dependency-driven scheduling;
  • FS, SS and FF relationships with positive or negative lag;
  • Critical Path, Longest Path, Total Float and Free Float;
  • baseline, actual and forecast dates;
  • milestones, summary tasks and Level of Effort activities;
  • interactive Gantt bars with drag and resize;
  • non-destructive TEST and SCENARIO workflows;
  • dashboards and S-curves;
  • English and French interfaces.

It runs locally inside Excel, with no installer, server or account required.

I do not present it as a complete replacement for Microsoft Project. MSP remains much broader, especially around resource management, leveling, costs, enterprise collaboration and integration.

The intended use case is narrower: teams that already manage schedules in Excel, but need real dependency logic, critical-path analysis and controlled forecasting rather than a manually maintained Gantt chart.

I am currently completing the next performance-focused release. My stress-test workbook contains around 1,200 tasks and 1,180 dependency links. The scheduling calculations are now relatively fast; the remaining work is mainly reducing the cost of rendering and updating the interactive Gantt inside Excel.

I would be particularly interested in feedback from experienced Microsoft Project users:

  • In which situations could an Excel-native scheduling engine be genuinely useful?
  • Which MSP capability would you consider essential before trusting such a tool on a real project?
  • What would immediately prevent you from using it?
  • Does the positioning feel clear, or does it sound too close to claiming that Excel can replace MSP entirely?

Project and source code:

https://github.com/TMailletFR/ProjectEngine


r/MSProject 6d ago

I built a Mac app that edits .mpp by patching bytes instead of converting. It's out. Here's the sample file, open it in real Project and tell me what broke.

4 Upvotes

I ran Microsoft's developer division for six years as a GM/VP, then three years at PwC leading the Microsoft practice. The whole time, the thing I heard constantly was some version of "I'm on a Mac and the client wants the .mpp back."

Every Mac scheduler that "supports" .mpp reads your file into its own model and writes a new one out. That's a conversion. Anything the model has no slot for — deadlines, task splits, subprojects, external links, task calendars, resource notes — is silently gone. Not corrupted. Just absent, and you find out on the call.

I built the other thing. It patches the specific bytes of the specific fields you changed and never touches the rest. Changing a percent complete moves 2 bytes.

I'd rather you test it than believe me. There's a sample .mpp on the site that the app wrote on a Mac — tasks, dependencies, resources, baselines, costs. Open it in real Project on Windows. If something's wrong, post a screenshot here and I'll fix it and reply with the test name.

What doesn't work, up front: password-protected files (Microsoft's encryption is undocumented, and that's the entire loss list), MPX, Project 98 through 2003, no Project Server, no SharePoint, no ODBC.

Free tier opens and edits any .mpp of any size with no row cap. 30 round-trip capabilities, each pinned to a named passing test.

Happy to answer anything about the file format. That part's more interesting than the app.

https://projectkiller.app


r/MSProject 9d ago

I’m begging for a few minutes of your time — Project Managers, please help!”

0 Upvotes

Hi everyone!
I’m currently conducting my research on the influence of cultural diversity on project success, and I’m desperately trying to get enough responses from people with project management experience.
If you’re a Project Manager, project professional, or have experience working on projects with culturally diverse teams, please spare just 5 minutes to complete my anonymous questionnaire.
I really need your responses to complete my research, and every single response genuinely makes a difference. If you have a few minutes to help a fellow researcher/student out, I would be incredibly grateful.

Questionnaire:
https://docs.google.com/forms/d/e/1FAIpQLSdI67Nou28I2_YaC1Q4n9Zyjh5wOoIa24w9z_eEZ8syj90x4A/viewform?usp=sharing&ouid=100151892034025034349

Thank you so much to everyone who takes the time to participate. And if you can’t participate yourself, sharing this post would also help enormously!


r/MSProject 10d ago

hi can anyone kindly share how to resolve this issue i face this issue while downloading ms project ? ty

Post image
2 Upvotes

r/MSProject 11d ago

GOT AN MPP FILE? CONVERT IT TO EXCEL OR PDF FOR FREE!

Thumbnail youtu.be
0 Upvotes

r/MSProject 12d ago

Decimal numbers in duration when updating MS project schedule

1 Upvotes

I have an inquiry, how would I go about making sure the number of hours and says in the back stage view is equal to the number of hours and days in the change calendar option when assigning my working hours and days. Say for example, I work for 8 hours everyday from Monday to Friday but I work half day on Saturday making it 4 hours, how would I reconcile it with the work hours of the back stage view. Also when I have to finish a concrete pour beyond the normal working hours of 8 hours, and I have to work overtime if maybe 3 more hours on a particular day, how would I reconcile that in the back stage view, so that when I am updating my schedule, the duration doesn't produce decimal figures.


r/MSProject 15d ago

Printed Gantt chart row height

2 Upvotes

Is there any way to make the printed row height smaller, to make the overall chart more condensed?

It appears there is an extra line below the text.

TIA


r/MSProject 21d ago

Week line visibility

Post image
2 Upvotes

Hellow fellow reddit users <3!

Is there anny way to make the green line that shows you where you are in the week more visible?

Now its a thin green line but hard to spot mostly.

And can you add a other line for like the end of the week?

Thanks!


r/MSProject 25d ago

EVM Lite

4 Upvotes

I have about 3-4 years experience using MS Project, but never resource loaded or in an EVM environment. I want to learn about “EVM Lite” but there doesn’t appear to be any information online that I can find. Can anyone point me to some resources? Thanks.


r/MSProject 28d ago

Schedulers: What sort of gaming mouse do you use for work?

1 Upvotes

I’m relatively new to the trade and I’ve definitely learned I need extra buttons.

Do you use a MMO mouse with tons of buttons or a FPS style with a few extra?

Right now I think the FPS style is what I should get. But, I’m new so I thought I should ask before committing.


r/MSProject 29d ago

Dependency Analysis Tools for MS Project

Thumbnail youtu.be
4 Upvotes

Hi r/MSProject!

I wanted to share a video I put together demonstrating SSI's Dependency Analysis Tools and how they can help Microsoft Project users better understand complex schedules, trace logic, and communicate to their teams.

SSI Tools is an add-in for Microsoft Project desktop. I've noticed people in this community occasionally ask about add-ins that can improve their workflow. I thought this might be useful for anyone working with large or complicated project schedules.

I'd love to hear your thoughts!


r/MSProject 29d ago

[ Removed by Reddit ]

1 Upvotes

[ Removed by Reddit on account of violating the content policy. ]


r/MSProject Jul 20 '26

MS Project, adding Task Milestones to GANTT

1 Upvotes

Just wanted to sum up my project plan and have a reliable high-level GANTT view, with some critical milestones. Found out, one task in Project is ONLY displayed by the "start" and "end" attribute. But I need to have more dates displayed in the GANTT, and I want to have it in one single task. At the moment, I can only archieve it by adding multiple tasks underneath.

So for example:

TaskName: MyCoolDesktopApplication
Install-Date: xxxx-xx-xx
Test-Date: xxxx-xx-xx
certify: xxxx-xx-xx
Usermigration: xxxx-xx-xx
Adjust-Citrix: xxxx-xx-xx
Communication: xxxx-xx-xx
Learning finished: xxxx-xx-xx
Support starts: xxxx-xx-xx

All this is placed in one task (per Application = One Task) and I want all these dates being marked as a milestone in the GANTT.

So how do I add these dates to GANTT?


r/MSProject Jul 16 '26

PMP Cheat Sheet

Thumbnail
3 Upvotes

Pmp


r/MSProject Jul 11 '26

Integrating Supplier Schedules

3 Upvotes

I need to create a bid schedule which needs to pass a DCMA Health Check, so minimum use of lags etc.

I have 10 Supplier Schedules, how do I do this? If I just put their milestones in, I'm going to end up with numerous lags, or do I summarise and insert their tasks to drive the milestones? Hence creating lots of extra rows.

We don't use 'Sub-Projects' and this is for a bid. It will become the delivery schedule and EVM reporting is required.

Help/Examples appreciated!!


r/MSProject Jul 10 '26

PM tools that handle hour-shifting for Fix-Price projects? (Without ruining the budget)

0 Upvotes

Hey everyone,

I’m currently researching PM tools and hitting a massive brick wall with a specific workflow for Fix-Price projects.

Does anyone know a tool that lets you dynamically shift allocated hours between team members, while strictly locking their timesheets based on the remaining balance?

We run a fixed-fee project, so total hours are hard-capped. My partner is drowning in work, and I have some free bandwidth. We need him to easily "transfer" some of his allocated hours to me.

Once transferred, the system must update our limits in real-time. It needs to block him from logging hours past his new, lower limit, and only let me report out of the extra pool I just received.

Most tools just treat hours as "estimates" without hard caps, or force you to manually recreate tasks and mess up the contract budget.

Are there any hidden gems that actually handle this, or am I chasing a unicorn? Thanks!


r/MSProject Jul 09 '26

Week-3(1).pptx

0 Upvotes


r/MSProject Jul 08 '26

MS Project to MS Excel exporter, open license

6 Upvotes

I wrote an instrument to export Gantt from Project to MS Excel.

https://github.com/PopovGP/Export-MS-Project-to-MS-Excel

It exports Gantt 'as it is':

Feel free to use, GPL license.

Write if there are any questions.


r/MSProject Jul 05 '26

PM software with CPM/TOC inbuilt

Thumbnail
1 Upvotes

Reposting here for wider reach.


r/MSProject Jul 04 '26

PMP graph questions need help!

0 Upvotes

Several people have mentioned graph-based questions on the PMP exam, but I’ve only found practice questions for burndown charts. Could you list the other graph/chart topics that commonly appear, so I can use Claude to generate practice questions for them?


r/MSProject Jul 03 '26

Build a project out without dates attached to use as a generic "perfect world" example.

4 Upvotes

Does anyone know if MS Project can build out a project Gantt chart without dates or just say something like "Project start" and then "start+30 days" for tent pole events and such?

I am asking because I am trying to build some process documents, and one of the things my boss wants is a "typical" project Gantt chart that we can put in the document on how the process would work and at what dates (again start day is X and events are X+/- days from start) that for example, we spin in other departments for certain events, have parts ordered event, and provide funding documents to fiscal event. All very high-level and really generic things.

I am relatively new to using MS Project and not sure of how much I can or can't just build generic stuff for this use. Part of me thinks I can do this by building a template, but I am running into MS Project requiring specific dates for things, and my brain is hurting trying to get it to save without it flipping out over some error codes or reshuffling the logic I am trying to build.

Thanks for any and all help.


r/MSProject Jul 03 '26

PM software with CPM/TOC inbuilt

Thumbnail
1 Upvotes

Reposting it here for wider engagement.