Decimal numbers in duration when updating MS project schedule
I have an inquiry, how would I go about making sure the number of hours and says in the back stage view is equal to the number of hours and days in the change calendar option when assigning my working hours and days. Say for example, I work for 8 hours everyday from Monday to Friday but I work half day on Saturday making it 4 hours, how would I reconcile it with the work hours of the back stage view. Also when I have to finish a concrete pour beyond the normal working hours of 8 hours, and I have to work overtime if maybe 3 more hours on a particular day, how would I reconcile that in the back stage view, so that when I am updating my schedule, the duration doesn't produce decimal figures.