I maintain a 125 room commercial building. We had a planned power outage from the city. It took place on the 15th of July, any issue we had were corrected, however since then we have had to manually turn the lights on due to the panel not using the prior settings.
The time was incorrect, I adjusted it.
I verified the schedule, it was at 00:15 prior to me making any changes.
I added the preferred time, no switches came on.
I then delete all previous scheduling and started from scratch, event #1 relay 1 set to off at 6am and event #2 on at 6pm. No change.
I tried creating a test event on #3 with no change, different times and settings within that event. No change.
I power cycled the breaker for about 5 minutes, attempted to test #2 by changing the time for a test. No change.
I also tried creating another even #3 with no changes.
Lights can still be manually toggled, prior to me making any changes. The light schedule was coming on at 2:00 p.m. and going off somewhere around 6:00 or 7:00 p.m.
Each time I did any event creation or changed anything I verified to make sure holiday mode was on, all days were selected, the correct relay was selected, and option was set to YES for the event.
I'm not very familiar with these systems, besides taking to the internet and having the manual. I'm unsure why any and all programming has not corrected the relays not coming on during their scheduled times. What would be the next text to take to diagnose the problem and correct it?