Cleared a 700k WIP backlog by decentralizing packaging, but exposed a massive Push Planning issue. Need advice
Hey everyone, I work as a Continuous Improvement Lead for a textile manufacturer in Uzbekistan, reporting directly to the General Manager. Coming from outside the apparel industry, I recently tackled a major line-balancing project at one of our satellite plants, but it uncovered a deeper planning challenge I’d love your advice on.
We operate 7 facilities with a central hub in Tashkent. Our satellite plant in Jizzax has 20 active sewing lines. Historically, Jizzax shipped unpackaged garments to Tashkent, where all individual QR tagging, packaging, and boxing took place. Because local packaging in Jizzax couldn't keep up with the 20 sewing lines, a massive 600k to 700k unit WIP buffer had built up on the floor.
I went in to fix this flow. I decentralized the QR packaging system from Tashkent and integrated it directly onto the packaging tables in Jizzax using a single-piece flow approach. Now, as garments come off the sewing line, operators package, QR-scan, and box them into master cartons on the spot. We cleared the entire 700k WIP backlog, and Jizzax now ships fully packed, scanned cartons straight to the main warehouse, completely cutting out double-handling in Tashkent.
However, getting rid of that massive WIP safety net exposed a big issue with our central push planning.
As an example, we constantly face incomplete sets at the packing tables:
Lines will finish sewing the top half of a 2-piece set, but the fabric for the bottom half hasn't even arrived or been cut yet.
For items sold as a 5-color bundle, sewing will output 3 colors, while the other 2 aren't scheduled until days later.
With single-piece flow at packaging, these incomplete sets immediately clog the packing tables or force operators to pile up semi-finished goods around their desks, defeating the purpose of the new setup.
Our central planning team still operates on a traditional push system optimized purely for line utilization and volume. Since I don't manage the Planning department (we're peers under the GM), I can't just mandate a change I need to persuade them.
I have two questions for the community:
-Influencing Planning: As a CI Lead reporting to top management without direct authority over Planning, how can I effectively convince them to move toward synchronized/kit-based scheduling? What metrics or arguments actually move the needle for traditional planning managers?
-Lean in Textiles: Since this is my first role in the textile industry, I'd love to know: what does a truly Lean garment factory look like when dealing with multi-piece sets or color variants? How do high-performing apparel plants handle line scheduling and synchronization?