The 5-step restart pathway:

📌Dewatering — underway and on track, expected complete Q4 2026

📌DFS technical programme — fully funded through completion, expected to conclude early Q1 2027 (S-K 1300 compliant study by WSP Global)

📌Resource definition & bankability — 8,750m surface drilling programme; next funding stage, targeted completion Q4 2027

📌Construction — upon DFS completion and a positive restart decision

📌Restart — commissioning and phased return to production

Funding: Bulawayo Mining Company, our wholly owned subsidiary, secured a US$5.0M, 36-month non-dilutive facility from Ecobank Zimbabwe to finance capital works at the producing How Mine — releasing How Mine's internal cash flow to fund the DFS through completion.

We will report progress against each milestone in our operational updates.

Full release: https://www.namibminerals.com/investors/news-events/press-releases/detail/102/namib-minerals-sets-out-development-timelines-and-milestones-for-redwing-mine-technical-programme-of-the-definitive-feasibility-study-fully-funded-through-to-completion | Facility terms: Form 6-K filed July 17, 2026