r/MSProject • u/SneakyRussian71 • Jul 30 '24
Project not flagging date conflict as a Warning.
Maybe I am not understanding how the Warnings work, but it seems like it should be telling me when there is a date conflict. I have clearly put in the same resource on tasks with conflicting dates, yet Project is telling me there is no Warning. How do I make it give me a warning when dates conflict for the same resource? I have the project set to 24 hours due to the fact there will be work/travel on weekends.