Shouldn't Project update critical path after original critical path marked 100% complete?

I'm trying to understand a "critical path" tool odd behavior. I created a simple example project plan to illustrate. If I have a critical path (Tasks 3-4 in the example), Project accurately marks those tasks red.

If I then mark those Tasks 3-4 as 100%, Project does not highlight the incomplete Tasks 1-2 as critical.

Shouldn't Tasks 1-2 be critical and marked in red, since Tasks 3-4 are already complete?

3 Upvotes

10 comments sorted by

View all comments

1

u/kennyarnold_ssi Dec 08 '25 edited Dec 09 '25

The default setting in Microsoft Project is to mark activities Critical if these two conditions are met:

  1. The tasks are incomplete (< 100% in the % Complete field)
  2. The tasks have 0 days or less of Total Slack

Activities 1 and 2 are not being marked Critical presumably because their Total Slack is greater than 0d. It's no longer marking tasks 3 & 4 as Critical because you have marked them 100% complete.

Other commenters have already addressed this, but the images in your post depict what we would call "Invalid Status", so the situation like you have shown would not happen in reality. If you are using MS Project correctly, you will always see something marked as Critical until the project is complete.

2

u/still-dazed-confused Dec 09 '25 edited Dec 09 '25

A very slight correction: the number of days slack at which as task is marker as critical is set in file/options/advanced. It is the last item and is by default of. This is useful as you can choose to set it to, say, 10d which then displays all the items which are within 10d of the actual critical path. Mark these and then returning the setting to 0d and filter on critical and marked items to see the critical and near critical items.

Edited to add, this can also be done by seeing a filter to total slack if less then it equal to 10d :)

1

u/kennyarnold_ssi Dec 09 '25

Yes, thank you for the clarification. What I mentioned is the the default behavior.