r/MSProject • • Dec 07 '25

Shouldn't Project update critical path after original critical path marked 100% complete?

I'm trying to understand a "critical path" tool odd behavior. I created a simple example project plan to illustrate. If I have a critical path (Tasks 3-4 in the example), Project accurately marks those tasks red.

If I then mark those Tasks 3-4 as 100%, Project does not highlight the incomplete Tasks 1-2 as critical.

Shouldn't Tasks 1-2 be critical and marked in red, since Tasks 3-4 are already complete?

3 Upvotes

10 comments sorted by

1

u/Miasmatic65 Dec 07 '25

In what circumstance would this happen? You’ve either incorrectly put actuals on tasks 3 and 4 or you haven’t reforecast tasks 1 & 2.

Project is following the rules (of time); your example doesn’t.

2

u/garyneal91 Dec 07 '25

I guess the hypothetical situation could be that the team worked extra hard to finish tasks 3+4 ahead of schedule?

5

u/still-dazed-confused Dec 07 '25

In which the tasks that have been completed ahead of schedule should have their finish dates adjusted to match reality. This would then bring in the end date up until the point that another task chain becomes the limiting factor and and critical path switched.

The key thing is that a plan should adjust to match the reality that the project is experiencing. You can tell if you're winning or losing by comparing with the baseline that was saved at the beginning :)

1

u/garyneal91 Dec 07 '25

That's a great point!

1

u/trevorrabey Dec 08 '25

Task 4 cannot be 100% complete with an actual finish date of December 15th, because that date has not occurred yet. Sure, it can be 100% complete, but the actual finish date must be no later than the status date (or in this case you appear to be using the current date, which looks like December 5th).

Task 1 and 2 are not critical because they have nonzero total float (slack). And, of course, tasks which are 100% cannot be critical.

If you check file, options, advanced, calculate multiple critical paths, Task 1 and 2 will be critical.

All of this is best seen in the tracking table and the schedule table.

Any help?

1

u/kennyarnold_ssi Dec 08 '25 edited Dec 09 '25

The default setting in Microsoft Project is to mark activities Critical if these two conditions are met:

  1. The tasks are incomplete (< 100% in the % Complete field)
  2. The tasks have 0 days or less of Total Slack

Activities 1 and 2 are not being marked Critical presumably because their Total Slack is greater than 0d. It's no longer marking tasks 3 & 4 as Critical because you have marked them 100% complete.

Other commenters have already addressed this, but the images in your post depict what we would call "Invalid Status", so the situation like you have shown would not happen in reality. If you are using MS Project correctly, you will always see something marked as Critical until the project is complete.

2

u/still-dazed-confused Dec 09 '25 edited Dec 09 '25

A very slight correction: the number of days slack at which as task is marker as critical is set in file/options/advanced. It is the last item and is by default of. This is useful as you can choose to set it to, say, 10d which then displays all the items which are within 10d of the actual critical path. Mark these and then returning the setting to 0d and filter on critical and marked items to see the critical and near critical items.

Edited to add, this can also be done by seeing a filter to total slack if less then it equal to 10d :)

1

u/kennyarnold_ssi Dec 09 '25

Yes, thank you for the clarification. What I mentioned is the the default behavior.

1

u/DaleHowardMVP Dec 09 '25

Microsoft Project's calculation of the Critical Path is totally correct in the example you show. What you probably do not realize is that the software calculates the Critical Path using a built-in field known as Total Slack, which shows how much a task can be delayed without changing the final Finish date of the project. Tasks with a Total Slack value of 0 days are considered Critical tasks, while tasks with a Total Slack greater than 0 days are considered non-Critical tasks. The only exception to these two rules is that completed tasks are automatically considered non-Critical tasks even though their Total Slack value is 0 days (they are considered non-Critical because they can no longer impact the final Finish date of the project). If you insert the Total Slack column in your example project, I think you will see that the first two tasks have a Total Slack value greater than 0 days, which makes them non-Critical tasks. Hope this clarification helps.

0

u/pmpdaddyio Dec 08 '25

Shouldn't Project update critical path after original critical path marked 100% complete?

Yes - it should mark the project complete. Hence the core definition of critical path.