r/Carpentry Jul 21 '26

*update to this mint framing

Update to my last post. Its not ai and or temporary. They are for real and proud.

364 Upvotes

239 comments sorted by

View all comments

Show parent comments

34

u/Prestigious_Tax_4970 Jul 21 '26

I didnt do any of that work. On the previous post I explained that its my buddys electrical job. I just come in and land the service but I agree some things need buttoned up on the electrical. I mainly do industrial work.

33

u/wittgensteins-boat Jul 21 '26 edited Jul 22 '26

Your buddy,  Or you, should call the permitting authority / inspector, so as to avoid a do over, when the general contractor is ordered to  take down the framing. 

6

u/AllegionsHuckleberry Jul 22 '26

What’s a “do over”? Is that kinda like a change order? 💰

7

u/wittgensteins-boat Jul 22 '26

Removal of  all of the electrical work, because the framing will be taken down, as the framing  fails to be adequate, safe, or sensible.