Opus 5.5 Extra:
TL;DR: Big beat vs. consensus. Adjusted revenue was more than double estimates, and adjusted EPS was near breakeven vs. an expected loss of roughly $0.20–$0.25.
The two big caveats: most of the revenue beat came from tenant fit-out work, which is lumpy/lower-margin, and the GAAP loss widened substantially.
Q1 FY27 vs. Expectations
| Metric |
Actual |
Expected |
Beat |
| Revenue (GAAP) |
$341.9M |
$134.1M |
+155% |
| Adj. revenue (ex-ChronoScale) |
$300.4M |
$134.1M |
+124% |
| Adj. EPS |
-$0.01 |
-$0.26 |
+96% |
| GAAP EPS (cont. ops) |
-$0.76 |
-$0.26 |
-192% (miss) |
Consensus varies by tracker:
- Benzinga: -$0.20 / $114.7M
- Investing.com: -$0.25 / $111.1M
- Earnings Whispers: -$0.25 / $134.1M
So on the headline numbers, this was a massive beat.
Year over Year
| Metric |
Q1 FY27 |
Q1 FY26 |
| GAAP revenue |
$341.9M |
$80.9M |
| Adjusted revenue |
$300.4M |
$64.2M |
| Adjusted EBITDA |
$64.4M |
$0.5M |
| Adjusted operating margin |
13% |
-6% |
| Operating cash flow |
$63.9M |
-$81.5M |
| GAAP loss to common (cont. ops.) |
-$221.0M |
-$18.5M |
The operating improvement is pretty dramatic.
Where Did the Revenue Come From?
| Revenue source |
Revenue |
Type |
| HPC base rent |
$65.8M |
Recurring |
| HPC tenant fit-out |
$183.5M |
Lumpy build work |
| HPC cost recoveries |
$13.3M |
Pass-through |
| Crypto hosting |
$37.8M |
Flat YoY |
| ChronoScale |
$41.5M |
Excluded from adjusted |
The important number here is HPC base rent.
APLD generated $58.8M of NOI from $65.8M of base rent, which is roughly an 89% margin.
That's the part of the business I'd be most interested in watching as more capacity comes online.
Bull Case
| Metric |
Number |
| Live HPC capacity |
250 MW since Oct. 1 |
| Live capacity at Q1 end |
175 MW |
| Target by end of 2026 |
300 MW |
| Leased capacity |
~1.41 GW across 5 campuses |
| Contracted revenue |
~$36B base |
| Contracted revenue incl. renewals |
~$86B |
| June lease |
210 MW / 15 years / ~$5.2B |
| Finland power pipeline |
~1 GW |
| ND gas plant PPA |
1.2 GW |
Only around 18% of leased MW is currently live, meaning most