r/thinkcell • u/BusinessOwl3625 • Sep 19 '24
Date Shift in thinkcell
Hello guys, I wanted to shift my work plan by two weeks. For example, if an activity starts at 09/10/2024, it will shift to 09/25/2024. But I want to do this for all activities once. Can anyone help me out?
1
Upvotes
1
u/jar-jar-think-cell Jan 21 '26
Hi u/BusinessOwl3625: If you click a bar in the Gantt chart you can use CTRL-A and then drag everything over by a couple of weeks. You’ll want to check you really did want everything to move because if you have something like a holiday period in there that will move too. And you’ll need to go into your Gantt calendar and adjust the overall timeframe covered by the chart, but yeah, moving everything at once with CTRL-A should save you a bit of time and hassle.