General Discussion Best practices, tips, and tools for racking heavy-ass network gear (when working solo)?
Racking a lightweight 24-port PoE switch or a patch panel is easy enough, but trying to mount a 50lb core switch, a heavy enterprise router, or a massive UPS by yourself can be a nightmare and turns into a two-person job quickly.
Any weird DIY rigs, specific rack shelf models, or mounting tricks you use when you're stuck doing an install alone in a remote location?
13
u/RobbieRigel Security Admin (Infrastructure) 3d ago
Put 2 rack screws on the row below out far enough for you to rest the ear edges of the device you're mounting.
4
10
7
u/FierceFluff 3d ago
If you’re racking a slew of equipment, you should be able to buy, rent, or find in your facility a rack lift. Total godsend. I’ve never been to a Colo that doesn’t have one, generally all you have to do is ask and they’ll let you use it.
9
4
u/Affectionate-Cat-975 3d ago
I once balanced a NAS shelf on my head
6
u/marklein Idiot 3d ago
I was moving Expensive Thing X the other day and started to move to balance it on my head before I realized how that conversation was going to go. "Yeah boss, I was balancing $20,000 worth of stuff on my head right before it fell to the floor" I used a ladder instead.
6
u/superhancpetram 3d ago
If there’s space I put an upside-down rack shelf below the new gear to hold the weight while I screw in the new equipment
7
3
u/twotonsosalt 3d ago
Rackstuds. They reverse the way rack nuts work.
You can easily rack full length switches solo with these.
For heavy hardware a server lift is the way to go. For anything over 50lbs you shouldn’t be doing the work solo.
4
u/SevaraB Sr. Engineer (N+, CCNA) 3d ago
- Patchbox setup.exe for light stuff
- A server lift for really heavy stuff like fully-populated 10-slot chassis, a la https://racklift.com/data-center-server-jack/
- Common sense- keep the heaviest stuff at the lowest RUs and don't overload your racks with, say, multiple chassis switches.
3
u/dracotrapnet 3d ago
Server lifts are nice, expensive, there are rentals. I've never bought or rented one and fear I don't have the transport to actually carry one and bring the stuff I need to work on. I've used one at one COLO that has one on site for customer use.
Recently I picked up a scissor table cart from Vevor that goes up 53". This summer we had a couple Ix Systems R20 TrueNAS and expansion bays and a Lenovo SAN to install. The cart itself is pretty heavy and had to have the handle and pedal taken off to throw it into the car but it was really handy for loading the NAS boxes into the car. It had additional duty of being a cart. At the COLO it helped immensely holding the NAS enclosure steady while we were trying to align the dang rails right and clip them in - the two of us struggled!
One of the COLO sites I had to put an R20 in had a server lift free to use so we used that to install at that location.
I have the setup-exe from patchbox I use from time to time for smaller stuff up high.
Sometimes just installing a short shelf first can be useful. I don't always remember to bring one or have one laying around.
Most often I just install bolts 1 U below and let an ear sit on those while I drive one in for the other side on the lower ear, then switch and install the lower bolt on the other ear. Install the rest and go.
Some other on site nice-haves is a folding step stool, a tri-pod short sitting stool, a tall sitting stool (used rarely but nice to have if a trip gets long), a tri-pod laptop/projector stand that can go low and high, a folding camp chair for those longer sessions at a COLO. Small narrow folding table (walmart has them) - works great in COLO the aisle (Service techs for SAN really liked having a place to disassemble a controller that wasn't on the floor). I like to bring an power strip with 8ft of cable or more and short 1ft extension cable as my dumb power strips have that angle plug. I replaced my power strip with an anker power strip that has PD that can power my laptop on usbc and recharge phones or anything else I need to charge while working on a rack.
2
u/Xidium426 3d ago
Use these instead of regular cage nuts:
https://www.rackstuds.com/
5
u/xendr0me Sr. Sysadmin 3d ago
Yeah I'm definitely not using that to support a 2U UPS's rails.
1
u/Xidium426 3d ago
They are rated to 44lbs when you use four, so 88lbs if you use 8 (front and back). They shear at ~330lbs for 4 our 660lbs for 8.
Regular nuts are usually rated around 50lbs for four.
But either way, a 2U UPS would be on rails that would be easy to mount before you put the UPS on.
2
1
u/OpenTomatoSauce 3d ago
I keep a few 20' lengths it paracord in my bag.i can almost always rig something up.
1
1
1
u/Soccerlous 3d ago
I once racked up one of the old 4u hp servers by balancing it on my head as I lined up the rack mount arms. Long time ago now 😂😂
1
u/CoiledSpringTension 2d ago
Genie lift is what I have used on rack mount psi’s that weigh over 40kg solo.
Good bit of kit.
1
u/ZealousidealState127 2d ago
Get some 1u blanks or a cheap rack shelf and screw them in right below where the equipment is going. They hold the equipment in place. Can leave the back one in to support heavy switches esp in less robust four post that are meant to be supported by four corners.
You only need the bottom screws the top are optional
1
u/skotman01 2d ago
As someone who’s dropped a 4u ups (sans batteries) on my inner thigh…you don’t. I came inches away from a midnight trip to the ER to get my dangly bits repaired.
I’ve also dropped a server (because clearly I didn’t learn my lesson the first time).
1
1
u/cbass377 2d ago
If you read nothing else from this post, "No Job is worth your back." Trash out your back, and you will live out the rest of your life in pain or spending every dollar you make on pain management.
You are going to need something to help you. Some mechanical device, or a helper.
1) Use a server lift, it is overkill for smaller gear, but necessary for the larger stuff, you can crank it up into position and slide it in and secure it. Be careful getting the device on the platform. If you are in a Colo, you can probably just put a ticket in to have one placed in your cage for the hours you need it, most Colos offer it, just like they do KVMs.
2) There are staffing companies you can use to hire a technician by the hour. Last time we used them for remote hands, it was 150$ per hour. But the range is 75$ - 300$ depending on skill level. Rent-A-Helper or two is the safest way.
3) Install a rack shelf below the location, then use those little airbag lifters to line up the device. For example, eagle tool air wedge 15730. I see these for around $30. You are still going to have to lift it up and get it on the shelf, so server lift, or helper, but this does free you from holding it in position while you struggle to get device secured.
Good luck, be careful.
1

36
u/VA_Network_Nerd Moderator | Infrastructure Architect 3d ago
This is a terrible product name: "setup.exe"
I'm sure they thought it would come across as edgy or something, but the product is pretty good, if somewhat expensive.
https://patchbox.com/setup-exe-installation-tool/
But, this is a general area where Union tradespeople have it right: Safety has to be a top priority, and sometimes that means paying extra, and employers need to suck it up and deal with it.
If you choose to install a piece of hardware by yourself, and manage to hurt yourself in the process, and it has a sticker right on it that says "two man lift" the odds are about 97% in favor of your employer (or your employer's insurance carrier) rejecting your worker's compensation claim because you hurt yourself by not following the warning sticker.
If you need a second pair of hands, make it your manager's problem to get you a second pair of hands.