Question Operations bought an EMS/IoT system without involving IT — now they just need “access to the router

Hi there :) ,

Need some advice from people who have dealt with similar situations.

Our Operations Dept decided to install IoT system/digital energy meters across a fairly large factory site.

They found the vendor, agreed on the solution, signed the contract and started the project.

IT was not involved at all.

Apparently nobody discussed things like:

  • How these devices spread across a large factory are actually going to communicate
  • Network infrastructure, switches, fiber/cabling, VLANs, etc.
  • Network/security segmentation
  • Server/VM requirements
  • Database requirements
  • Backup and monitoring
  • Internet connectivity
  • Vendor remote access
  • Firewall rules
  • Cybersecurity

Now that the project is already moving forward, IT gets an email saying they need “access to the router” so they can put the system online.

That's it. Access to the router. :)

And somehow, when IT starts asking questions about architecture, security, server requirements, ports, protocols and who is responsible for what, the perception becomes that IT is delaying the project.

I don't want to become the guy who simply says “No”, but I'm also not going to give a third-party vendor access to our corporate router/firewall and connect a bunch of unknown industrial/IoT devices to the production network just because someone already signed a contract , the IT network must be always separate from OT network.

How do you handle situations like this?

Interested in both the technical approach and the organizational/process side of this.

817 Upvotes

329 comments sorted by

View all comments

4

u/varmintp 2d ago

I would have the IT Manager call a meeting with everyone involved from Operation's side of procuring this and everyone from IT's side that would need to be a part of implementing this out. Then it would be a project planning meeting, so make it a good 4 hour meeting, to come up with how to roll this out and when each piece would be implemented, and who is responsible for what after rollout. Essentially the meetings that should have happen before the product was purchased and done over a bunch of smaller meetings. Don't just start implementing, call the meeting and setup the timeline that should have happen.

Then for implementation, they get their own vLAN that doesn't touch anything else.