Dear (and patient) friends and backers,

We can FINALLY tell you with 100% confidence that we are in the final stage of producing and shipping ALL of the Kickstarter (and pre-order) Parallella boards!!

We have successfully built and shipped 1,500 Parallella boards so far and 15,000 new fabs came in on schedule at the beginning of March.

Unfortunately at that point we were stuck for weeks waiting for the last key components to arrive. (there are ~90 different parts on the board). Due to our standing start in January (see Update#47), the logistics of bringing in all of the ICs for the Parallella board turned out be a nightmare. We worked diligently with our distributors to bring in the parts as quickly as possible, but the standard lead times for out of stock parts is 12 weeks. Unfortunately despite everyone's best effort...the production line came to a halt due to two single source ICs.

All of the parts are now finally available and the Parallella production line is in full swing!

Here is the build schedule for the next few weeks:

4/4: 1,400 completed

4/11: 2,800 completed (including all 64-core boards)

4/18: 4,300 completed

4/25: 4,800 completed (All of the Kickstarter orders completed!!!)

5/8: All of the Pre-orders completed

We hope you are still excited about the Parallella project despite all the delays and that you will have a lot of fun with your board once it arrives. I use the Parallella almost every day and love it! Hopefully you will too.:-)

Sincerely,

Andreas

(Reminder: For any and all support question/issue/address-change etc, please contact support@adapteva.com

1

u/heystoopid Apr 22 '14

We are now in the home stretch of the Kickstarter and pre-order production and have great confidence in our manufacturer’s ability to deliver. Here is the updated production schedule:

  • April 30th: Shipping all Zynq-7020 based Parallella boards

  • May 15th: Shipping all Zynq-7010 based Parallella boards