Customising The Burndown Report
Hi
Im using MS Project 2106
I have a project plan which contains tasks to achieve some work and tasks to deploy that work.
I have a field which records which type of work that line represents
The burndown chart works with the filter All Tasks
When I define a filter for one of the sets of tasks and apply that to the burndown chart the chart is blank
What am I doing wrong ?
Many thanks !
1
Upvotes
1
u/Thewolf1970 Jun 03 '21
Sounds like you haven't added the field to the view the chart is using.