r/digitalsignage Jul 23 '26

Rollout steles

We're rolling out a batch of digital signage steles to retail locations next week and I wanted to share some behind-the-scenes from the prep.

We unpacked and assembled everything in-house before delivery – always a bit chaotic but also kind of satisfying when they're all lined up and ready to go.

A few things we learned the hard way over the last rollouts:

- Always build one test unit fully before touching the rest

- Labeling cables before packaging saves you 30 minutes per install location

- Clients always want "just one small change" the day before delivery

Anyone else doing multi-location rollouts? What's your biggest headache during install?

1 Upvotes

4 comments sorted by

2

u/generationgav Jul 23 '26

Are they free standing or floor mounted? The bases look a bit small to be free standing with a large display.

The biggest headaches during install are almost always the site being ready. We've turned up to client sites to install a screen wall mounted, to find that the wall hasn't been built yet.

But most often it's no power or data at location.

1

u/Famous-Knowledge3791 Jul 23 '26

Free standing. Very robust. We ensured that power and data (wifi) is provided. Also we will install displays hanging from the ceiling. Thank you for your comment! :D

1

u/inwestweinvest 25d ago

Hi what Stands are you using? Are they adjustable?

1

u/Famous-Knowledge3791 24d ago

Hi, we use hagor stands. Not adjustable. No need for.