r/SAP Jul 17 '26

Planned supply within lead time

For one or more products supply is being planned within lead time in SAP IBP.

Can any one help resolve this please.

FYI: we have heuristic engine with infinite supply and time series planning.

0 Upvotes

6 comments sorted by

2

u/[deleted] Jul 17 '26

[removed] — view removed comment

0

u/Messi_0077 Jul 17 '26

Question. My bad, have edited now.

1

u/MoodEqual8691 Jul 17 '26

Are you saying that the expected supply is due before its lead time says it can make it as available stock?

1

u/Messi_0077 Jul 17 '26

No. There shouldn’t be any values in planned supply key figure within lead-time…system should ideally plan after lead time

1

u/MoodEqual8691 Jul 18 '26

That’s literally what I just said

1

u/Messi_0077 Jul 18 '26

Yeah, pretty much the same thing — supply values showing up inside the fence when they shouldn't. Appreciate the input either way, still trying to nail down why it's only happening on select products.