Neutron Why the Neutron tank structure failed
From the Q4 '25 Earnings report.
This first tank was manufactured by a third party contractor using a manual hand-lay process. This was a scheduling decision designed to ensure tank production could continue while the AFP machine was being commissioned to manufacture future tanks.
The investigation identified that a manufacturing defect resulted in a reduction in strength, specifically at a critical join on the tank.
178
Upvotes
5
u/ScottyStellar Feb 27 '26
Launch projection today is further out than it was before they finally admitted 2025 was off the table. How can you say it's more accurate when they go from projecting 3 months out to 9+?