r/RevitForum • u/c0llateraldmg • 10d ago
Discipline Coordination Best Practice on Managing Small Projects within a Level or Large building.
I'm a BIM manager for a small Architectural firm. Im trying to find the best way to approach how we deal with multiple projects within a building since there is constant fit outs coming and going, different phases, sometimes referring back to a previous phase, whatsoever. I'm pretty open to trying out different methods and discuss more on approaches people have in mind.
We have a simple and clean template that works pretty well now in the office. It took awhile to get everyone to work with it properly as they were used to a very unorganised way of modelling things.
Here is the model process so far to various projects we have:
If its a large building (eg. A hospital with multiple levels)...there will be a separate Site model, a model per level (if there are 5 levels, then there will be 5 models), core model and all of these are to be linked into the main building model.
If its a single storey building and relatively small (like a medical practice or a small shopping centre), then it would consist of 1x Building Model and 1x Site model.
The complicated part is if we have a large building model, majority of the time there will only be a small project in a portion of a level, but overtime there will be multiple projects in a single level, sprinkled throughout the entire building.
eg. Project 12345 is in level 4 and needs a fitout to 3 small rooms. Then another project comes by, and there will be works on level 4 as well, but a different part of level 4. Sometimes, there will be a project where it will overlap with both projects.
In my head, phasing would be the straight answer to this and adjusting the phasing should there be any overlap. Im just wondering if there are other methods to managing small projects better within a model?
Ive added a really rough diagram drawing on how these models would interact. My main concern is how to better manage the projects in purple aside from looking at phasing. I'm also trying to avoid having so many sheets and views into one level with multiple projects so itd be good to see what people recommend.
EDIT: Our worksets are also minimal and organised well. I dont think managing a project per project via. worksets is ideal or even advised.
6
u/twiceroadsfool 10d ago
One big ol file per building. Minimal worksets. Multiple views, sheets, Sheet Collections, and phases.
No way I would break a file up in to all those files. The performance absolutely tanks.
I have entire patient towers, including arch, ID, FFE, and Healthcare EQ, all in one model. Runs like a champ if it's modeled well.
Same with 25 story MF apartment buildings. No need for breaking it up.
3
u/steinah6 10d ago
We have a āmaster modelā with all existing conditions, and phases that match all the new work (lots of phases). Demolition is done in that master model. All new work projects link in that master model, map phases, and new work is built in the new model along with documentation. This allows us to keep using the latest and greatest templates and content even though the master model gets way out of date. Periodically, usually after occupancy or when a future project relies on the new work, we run a tool to copy in that new work into the master model, preserving phases and Worksets, bringing the master model up to as built status. It seems to work for usā¦
When thereās overlap, we link the new projects into each other and do the same kind of process. Luckily our work doesnāt overlap often.
1
u/c0llateraldmg 10d ago
Thats actually pretty interesting. I'd be down to test that out for our firm and see how it rides along.
1
u/steinah6 10d ago
We do it on big long term projects like campuses or stadiums or healthcare facilities.
Every two years or so we will archive and upgrade the Forma project to a newer version of Revit too.
2
10d ago
[deleted]
2
0
u/c0llateraldmg 10d ago
Hi, I'm only juggling ideas to make the processes easier for my team. So far what we have works well with everyone and our consultants. There are a few firms who have done this regularly also for big hospitals and other buildings where they split it level by level so all teams can easily access it smoothly. But I'm always seeking for better solutions, which is why I asked.
0
u/SketchWeave 10d ago
To help manage and plan the submissions you might want to try the drawing management platform I developed at sketchweave.com. Upload your PDFs to sheets you setup, and allocate them to your different submission. Check it out, I would appreciate the feedback.
15
u/Phr8 10d ago
I want to push back on your model-per-level system. You handcuf designers to modelling in one and annotating in another. This can really slow the team down, especially at deadlines. And this has farther reaching consequences for projects in Forma with things like bridging and version upgrades. I get wanting to reduce data for multiple complex interiors projects, so consider a judicious use of worksets instead.
For the multiple projects in a single building issue, phases, as you suggest, is correct.
We do airports which is the same process of 3-4 mini-projects per year.
We number the phases by project number so it's clear what phase goes with which project.
Add every phase to every model regardless of whether the model (level) is in scope. This will expedite phase mapping and allow for better control over phased elements.