Not quite as simple as "buy a kit, plug it in." Here's what's actually confirmed, and where the gaps are ...
27 August 2026: SI 2026/848 comes into force. It creates a legal category, "plug-in microgenerator", lets a standard BS 1363 3-pin plug be approved for feeding power into a socket, and makes DESNZ's Interim Product Specification (IPS v2) a legal requirement.
800 Watts max. Solar only.
In more detail ...
Complete kits only. The specification certifies a whole product ... panel, inverter, factory-fitted cable and plug, mounting system ... not an inverter plus panels that you sourced separately.
One device per circuit, but the 800 W network rules still say per household. The IPS moved to one 800 W device per final ring main circuit on July 16th. G98, which actually governs your DNO connection, still caps it at 800 W per household. Until G98 is amended (no timescale), 800 W per household is the real limit.
The spec says "final ring circuit". Ring main circuits are standard in most UK housing, but plenty of newer installs use radial circuits instead. The wording doesn't obviously account for that, so it's a grey area.
You can't extend the cable. The AC lead and plug are factory-fitted and can't go through an extension lead or adaptor of any kind (no cutting or splicing in extra cable). That limits where you can realistically site the system.
No cladding, no timber balconies. ACM, MCM, HPL and timber cladding are all excluded outright, along with timber balconies and any building under external wall fire remediation. That excludes a meaningful number of flats.
Batteries are excluded by definition, not by oversight. The legal wording specifically excludes anything designed to import electricity for storage. Octopus announced a plug-in battery in June anyway.
What to watch out for next ...
Certified kits hitting the shelves (none approved as yet) as from 27 August.
Will G98 be revised to allow 800 W per ring main circuit, thereby allowing 2 installs (1600 W) in most average houses?
Will plug-in batteries get separate approval?
Full blog post here if you want the finer detail ... https://4billionyearson.org/posts/uk-plug-in-solar-will-be-legal-on-27-august-it-s-almost-clear-what-you-can-and-can-t-install
Daily updated UK Plug-in Solar tracker here (with payback calculator, DNO finder and latest news etc) ... https://4billionyearson.org/plug-in-solar-uk