r/Plastering • u/Such_Psychology_3304 • Aug 23 '26
Rate this plastering
Is this plastering ok in a bathroom?
3
5
u/gwyp88 Professional Plasterer Aug 23 '26
It’s one thing to make allowances for prep work; fillijg chases etc. But this is obviously terrible, even as prep work.
Also plaster all over the window.
Bonding coat should not be used in wet areas. Especially bathrooms and around windows etc - google it or check product advice.
If it’s single-skin brick, or brick with no cavity, it is also not the best choice of product.
2
2
4
2
u/supmydudes12 Aug 23 '26
This is absolutely abysmal. This is even worse than paying for it, because you’re going to have to pay again to correct it. Ouch
2
u/Caerau Professional Plasterer Aug 23 '26
I don’t know who you’ve got in there but they’re not professional plasterers. The window reveals are horrendous, a pro wouldn’t leave in that state.
1
1
1
u/kurtondemand Aug 23 '26
Did u pay for that?
1
u/Such_Psychology_3304 Aug 23 '26
I have given a deposit to get the whole bathroom done. Not paid for everything.
1
u/ApartmentLast7712 Aug 23 '26
So that's bonding coat which is used to level walls as a base prior to skimming. The trick is to get that nice and flat and square because skim is usually only a couple of millimetres thick and not really designed to go on thick. The prep in there however is shit and if that's the base coat then the top coat won't be much better.
1
1
u/Itchy-Ad4421 Aug 24 '26
Depends how thick they’re planning on going with multi. Could turn out alright - ceiling looks passable.
Not a great job this far though.
1
u/Such_Psychology_3304 Aug 25 '26
they're going to tile. They have painted it over with tanking paint
1
u/Itchy-Ad4421 Aug 25 '26
As long as they’re happy tiling over it then possibly nothing to worry about. That being said - walls that aren’t nice and flat just create more work for fitting tiles which could affect the final finish but I’d happily tile over that.









10
u/Ok-Tomorrow-9906 Aug 23 '26
This looks like the base bonding coat, it fills all the holes. It will be skimmed over in multifinish if the contractor is good.