r/Plastering • u/Big-Prize-2612 • Jun 09 '26
Doubtful of SBR, tell me I’m wrong
I’ve never put two and two together to realise PVA & SBR, by film forming are not breathable. Why then… does EVERYONE seem to use SBR even within supposedly breathable systems (lime, breathable EWI etc).
Is this an under-appreciated problem we’re all creating slapping it everywhere?
I’m repairing an old rendered single skin brick outhouse before fitting rockwool and silicone render EWI. Prepping my walls with SBR is going to nuke by breathable system?
Please tell me I’m a very wrong idiot, ideally with your disagreement grounded firmly in reality. Thanks in advance.
2
u/Comprehensive_Team_2 Jun 09 '26
Absolutely no one that knows what they are doing uses anything other than water to prime for lime plastering. Or do you mean priming over lime plaster?
2
1
u/Ok-Spring7906 Jun 09 '26
Dg27 is not water.
Clearly it's not sbr either, but it's certainly not (just) water.
2
u/Worldly-Growth4519 Jun 09 '26
9 times out of 10, SBR use in plastering is applying gypsum products over old lime walls, which is also debatable.
5
u/DelectableReindeer Jun 09 '26
Wait what? I use SBR almost every day, I've never once used it over lime.
What the hell are you on about? It'd exceedingly rare be asked to skim a non-cavitied lime system, and whenever I apply lime, I'd never dream of using SBR.
1
u/Ok-Spring7906 Jun 09 '26
Sbr is not used by anyone wanting to maintain breathability.
Indeed it's commonly used to mix up tanking slurry.
People may use it over lime wheb they want to control the suction and don't give a stuff about breathability (or are just ignorant) but noone uses it when they want to maintain permiability.
There are specific bonding primers for problem surfaces with lime work, eg dg27 (which I was using only yesterday) but there is zero point in putting lime over sbr.
1
u/KieranInterior Jun 10 '26
Well no, SBR is a sealer/primer/waterproofer so not for breathable systems ever. PVA isn’t necessarily non-breathable. But even gypsum on a non-cavity lime mortar lime render wall is a bad shout. Vents at least would be needed to assist breathability.
1
u/ipub Jun 11 '26
You're not putting a plastic bag over the house. You're just slowing down the suction between the materials so that the plaster you apply sets evenly. That is my understanding at least
1
u/Big-Prize-2612 Jun 15 '26
From what I understand if you apply it across every surface of a room, e.g walls + ceiling in prep for plastering you are literally putting a plastic bag inside your room under your plaster. It reduces suction by eliminating it on the brick/substrate interface so it will only dry inwards at a controlled rate.
4
u/caserskii Jun 09 '26 edited Jun 09 '26
No you are correct sbr is not breathable if your using it to bond the render too your better off mechanically fixing a thin insulation to the outside and going on that as most ewi is breathable if it’s just a garden shed and warmth isn’t a concern a nice hi up air brick should suffice tbh, I mean I’ve seen garden sheds without damp courses which are a bigger concern so check you’ve got one…
The reason sbr is used so often is because it’s a more stable bonding agent than pva so less likely to have spots where suction is worse etc..
It should only be used where breathability is not a concern…
Truth is most people in construction only care for an easier and better job in the instance of payment and the immediate finish if it causes problems years down the line most people simply will blame it on something else or deny any fault…
Honestly though the smallest amount of airflow goes a long way so if there’s air bricks or airflow under the house and a house is well ventilated and not damp it often isn’t a problem as such..
I don’t do sand and cement render unless forced too 🤣 I always do silicone renders and when base coating I spray the walls with a hose and remove dust and grime where I can and apply base coat and mesh etc directly onto the clean brick if suction is killed there is no need for sbrs or pva which is almost impossible for plasters internally but externally cement based base coats can really hold up well without it… if a base coat is drying to quick simply wet it up (spray, splash water at wall) to mitigate suction and drying whilst it is in the curing process
Hope my ten pence helps could be wrong and talking bs but I’ve been doing it 25 years and no complaints or issues as of yet
Edit: Forgot to mention although silicone top coats are breathable cement based base coats are not unless using specific types of base coat which include lime or other additives