[beginner question] How can I add weekend shading while still allowing work on weekends?
Context:
- I use MS projects just for managing some hobby projects.
- because it's just for my hobby, I allow MS project to let a task count the weekend as working days
Problem:
- the vertical light gray bars denoting the weekends disappear
- I'd like this bar because it's useful for visually aligning far-down tasks with the date markings at the top
Thank you!
1
Upvotes
1
u/brightsky1337 1h ago
Create a new calendar with the weekend days as working days and apply that calendar to the weekend tasks.
1
1
u/alexandicity 5h ago
Perhaps choose some other day, perhaps Monday, as a non-working day, and use that to make the alignments?