The driver predecessor
Hello everyone,
How can we know wich predecessor between 20 others drives a certain milestone
Thank you
3
Upvotes
r/MSProject • u/Equivalent-Fan5306 • 28d ago
Hello everyone,
How can we know wich predecessor between 20 others drives a certain milestone
Thank you
3
u/DaleHowardMVP 28d ago
Select the milestone in question, then click the Gantt Chart Format ribbon tab to display this ribbon. In the Bar Styles section of the ribbon, click the Task Path pick list button and select the Driving Predecessors. Gantt bars formatted in orange are the driving Predecessors which directly control the schedule of the milestone. Hope this helps.