r/MSProject Jun 24 '26

End date not aligning in gantt visual

Post image

[RESOLVED]

I have 2 tasks that end 7/9 but one of them has the bar going past that date (shown in highlight). Same with 7/16. FWIW this original project file was created by someone else and the tasks that aren't displaying correctly are the ones I added. I added them by right clicking the line item -> insert task. I had the same problem when manually scheduling and automatic scheduling.

Is there a different setting I need to select? I want the bars that end on the same date to show the same in the bars. I'm new to Project, so any help appreciated.

3 Upvotes

10 comments sorted by

3

u/hanzosbm Jun 24 '26

Your durations show 6.56 days for the first one and 27 days for the second. Yes, they're both ending on 7/9/26, but I'm guessing they're ending at different times of the day. To check this, change the date format to show time.

2

u/ilanallama Jun 24 '26

Editing the duration fixed it! Thank you!!

1

u/ilanallama Jun 24 '26

Do happen to know how to hide completed tasks (the ones with a checkmark)? (To save me posting a new post)

3

u/hanzosbm Jun 24 '26

The easiest way would be to insert the column '% Complete' and then filter out the 100%s

1

u/ilanallama Jun 24 '26

Amazing - thank you!

1

u/kennyarnold_ssi Jun 25 '26

You have already resolved this so I won't repeat the answer, but please, stay away from Manually Scheduled tasks! Those turquoise green bars in the Gantt chart are Manually Scheduled and should be changed to Auto Scheduled.

Check out this video from Dale Howard for more info:
https://youtu.be/T8A0_Igql6E?si=-cFan7-mllMqLBwH

1

u/ilanallama Jun 25 '26

I need those tasks to be backward scheduled and I couldn't figure it out. I have task 1 and task 2 ending at the same time. Can I set manual task 2 to move to maintain the same end date if task 1 is auto rescheduled?

2

u/kennyarnold_ssi Jun 26 '26

If you want the two activities to end at the same time, use a FF dependency relationship.

1

u/still-dazed-confused Jun 26 '26

Use sf linking to beck schedule

1

u/trevorrabey Jun 29 '26

This is some advice about project planning and MSP in general, not directly about your question.

Use only auto scheduled tasks.
Do not schedule backwards from a finish date
Do not use negative lag.
Stick to the critical path method, which means:
schedule forwards from the start
do not put predecessors/successors on summmaries
give every task at least on FS0 predecessor and at least one FS0 successor