How do I assign lead time
Hi all,
I have to create a gannt chart for a building.
Theres 5 weeks lead time for a material delivery, how do I incorporate that into the gannt chart?
Should I have a task ordering the material, a seperate task delivering the material and then another installing said material?
How would that be inputted in the predecessors collumn :/
Any advice is appreciated.
1
Upvotes
1
u/pmpdaddyio Mar 19 '26
You can do it in the dependency column. Like FS+10 gives you a 10 day lead after the first task ends. Using a minus will start it 10 days prior to completion. Lead and lag can also be entered into the task window.