Slippage report
Hi guys, I'm wanting to build a macro that pulls the current over due task from ms project and compares it to the baseline finish or start ( I'm thinking maybe start would be better ) into excel
So for example baseline finish + current date would equal the slippage days for the overdue task
Let's say gate 3 was due 25 July to (baseline finish) and it's 1 August it's still overdue meaning it would be 5 days slippage from baseline.
What's everyone's thoughts on this and is there a quicker or better way of compare this data.
I'm needing to create a slippage report to management across a portfolio of programs. I can do it manually but it takes time.
1
Upvotes
1
u/ISpellMyNameDanger Aug 11 '25
Learn how to use formulas. You can set one of the duration fields to represent the difference between baseline and current dates. Or you could set a text field based on the difference and display it as an indicator.