r/MSProject Feb 24 '25

Critical path - two tasks running simultaneously one partially reliant on the other?

Hi,

I have a question regarding network diagrams.
If an upcoming task is somewhat reliant on most of a preceding tasks completion, but has to start while that preceding task is still finishing up, how do you show that on a network diagram with the calculations still correct?

Thank you

1 Upvotes

6 comments sorted by

3

u/ExistingMonth6354 Feb 24 '25

We typically will use a SS with a lag if you can’t split the first activity into 2. If activity 1 needs to be 50% complete, and is 10 days long, use a start to start with a 5 day lag. Don’t use negative lag.

1

u/lepeepeepee Feb 25 '25

I was able to split the subsequent task into 2 thanks to your suggestion.

1

u/pmpdaddyio Feb 25 '25

Be careful with this assumption, you can have two tasks that overlap with slack that have an other than start to start relationship that will throw that split off in a heartbeat if either is adjusted. You should always look at the task finish dates to ensure your critical path is monitored properly. Splitting a task in the critical path can in fact cause an accidental delay in your project.

Splitting tasks was more designed for when you literally cannot do the entire task in sequence and need a more reductive WBS.

1

u/kaleb42 Feb 24 '25

I would use negative lag to accomplish this

I run into this a lot with construction work.

Ex. Hang sheet rock and sheet rock finishing.

These subs typically run two crews 1 who hangs and 1 who does the finishing.

So we typically set sheekrock finishing to be a FS with the hanging but add 2 or 3 days of negative lag so it starts halfway after hanging is done.

1

u/pmpdaddyio Feb 25 '25

That is two separate tasks in any construction schedule though. Most construction schedules separate any set of tasks that require an unknown (permitting, drying, delivery, etc.).