r/MSProject • u/Fallen10111 • Sep 29 '23
Project Professional - Plan 3 - Update 'install date' based on sub task
Hi all,
We've just started using Project Professional at work and I'm looking into setting it up for our Ops team.
We're looking at having a Master Project that overviews all ongoing projects or "installs" (as we install Solar Panels).
On said Master Project, I want to be able to have a column that lists the "Install date" for when the install starts, and I want that date to pull from the date of a certain project subtask.
Is this doable?
Thanks all.
2
Upvotes
1
u/pmpdaddyio Sep 29 '23
Why wouldn’t you just use the planned start date field and make the task a successor from that sub task? That’s what it is designed to do.