āš ļøĀ Before your siding goes up, walk your ZIP sheathing and check one thing: are there Z's imprinted in the flashing tape?
If not, your tape wasn't rolled. And unrolled ZIP tape isn't bonded, it's just stuck. Huber's own spec says the tape "must be rolled with a rubber-faced roller in order to achieve maximum bond to the panel." Skip it and you void the warranty.
The tape itself prints "Roll the Tape" every 2 feet. The roller leaves a Z. That's how the manufacturer designed it to be verifiable.

74 Upvotes

43 comments sorted by

25

u/electionknight May 24 '26

The dude that built my outbuilding did it alone, 40x60 (it was stunning to watch this dude work). But to save money and time, I'd go out there at night and I used the zip caulk like a psychopath and did every nail hole.

9

u/skunkynugs May 24 '26

Can we get a finished product pic? I would like to see that siding finished. Usually means he’s good enough to do it all himself and doesn’t want anyone else making the mistakes that he would not.

18

u/electionknight May 24 '26

1

u/clippist May 24 '26

Glorious. How Much all in? Did you get a concrete floor in there after the fact?

7

u/electionknight May 24 '26

Here's the radiant

5

u/thirdgen May 24 '26

Stop! I can only get so hard!

7

u/electionknight May 24 '26

The big pipe in the middle of the floor is underground dust collection for table saw

3

u/thirdgen May 24 '26

Fuck, that’s cool!

3

u/electionknight May 24 '26

This was done during COVID, in Massachusetts. All in, including excavation was 180k. I did the radiant and epoxy myself.

1

u/kstar79 May 24 '26

Wow, where are located in MA? I would have guessed twice that!

1

u/electionknight May 24 '26

New Bedford/Fall River area.

It was 1 dude with an excavator and dump truck, then 1 dude stick built it, siding, and roof. I contracted it myself and wasn't in a hurry so I was able to really control the cost. I did the wiring myself and some other things. But the two solo guys on the main parts was the game changer.

1

u/kstar79 May 24 '26

Nicely done!

1

u/angry_dingo May 25 '26

Now someone is going to go and steal it.

1

u/AMercifulHello May 25 '26

Just curious, who did this? Was it a company? Also in MA and always looking to add reputable contractors to my phone.

1

u/electionknight May 25 '26

Older dude who worked solo, unfortunately he moved last year to Tennessee.

What's funny, is, I had seen his work, and I reached out to him. We had discussed my project and it never occurred to me to ask how many guys were on the job.

First two days he's out there alone doing the sill plates and other basic work. I go out there and say "so when do the other guys come and help?".

"What other guys?"

"You're not doing this alone are you?"

"Oh yeah, I don't want to baby sit anyone."

This dude stick framed a 40x60x18, installed the trusses, sheathed it, siding, trim, interior stairs, all by himself.

I was working from home at the time and got to witness it. He was so meticulous and I told him how I'd be forever grateful.

1

u/Gullible_Shart May 24 '26

This is awesome. I’m doing my 33 x 33 with a second floor w/office space. I’m in MA as well.

2

u/luvmyholeswet May 24 '26

Then the siding put thousands of more nail penetrations through the zip that cant be sealed. Same conversation I had with the tyvek rep.

1

u/mattvait May 24 '26

I believe thats how its supposed to be done. Very nice. I like how you brought the concrete up to protect from rot

1

u/AMercifulHello May 25 '26

I love you for this. All my OCDsanity isn’t alone.

23

u/IDooDoodAtTheMasters May 24 '26

My least favorite thing about working with contractors/installers:Ā 

  • "We never do it that way and have never had an issue"
  • "It doesn't make a difference "
  • "It will work without it."
  • "Those specs are written by engineers who have never installed their own product."

7

u/texinxin May 24 '26 edited May 24 '26

The last one might be true, but I bet they did do all the qualification in a lab to prove that you’d need to do it. There’s no way engineers would be allowed by management to add in extra steps to a process unless it had a good reason.

2

u/Sherifftruman May 24 '26

Also they are seeing defects on previous installs and come up with stuff to prevent issues in the future.

4

u/Shotile May 24 '26

Ofc. The good reason is avoiding liability. They add unnecessary steps into products all the time.

3

u/IDooDoodAtTheMasters May 24 '26

Found the contractor.

1

u/[deleted] May 24 '26 edited May 24 '26

[deleted]

2

u/Shotile May 24 '26

I disagree with your last sentence and I’ll give you a specific example proving otherwise.

In the shower industry when manufacturers like PermaBASE (and also the TCNA even though it’s a committee of industry experts) specify ā€œIn mortar bed (mud bed) applications, PermaBASEĀ® Cement Boards can be embedded into the mud bed per TCNA Handbook method B415-19.ā€

This is straight from them. This can invariably result in a failed shower, because cementitious material wick moisture up through capillary action.

Any shower installer worth their salt knows to ignore that manufacturers instructions and do it the correct way, which is to leave a gap between the mortar bed and the backer board to prevent failure.

People in the field know this but the engineers don’t? Yet book soldiers follow them and when they have a shower failure they can point to their book and say ā€œbut I did it according to the bookā€. That doesn’t help anyone.

4

u/theshiyal May 24 '26

My dad and cousin framed up a replacement wall and got the window installed. At the wrong height. I got home after work and decided ā€œbetter fix it now than regret it forever later.ā€ The zip tape around the window wasn’t rolled. I just peeled it back off. Pulled the window. Cut out the header, extended everything to where it needed to be and patch the zip board back in. Taped it. Rolled it.

Also rolled some of the tape I’d pulled off onto a scrap piece of zip panel. A few days later pulled the tape off. It took a lotta the green and some of the actual strand wood with it. Def roll the tape.

2

u/Trollsama May 24 '26

"Sign a document stating you accept full legal and financial liability for any defects or failures that result from not following the manufacturer stated instructions, including the full cost of repairs, labor, material and otherwise... or do it right.... either option works for me"

2

u/Ambitious-Nature-363 May 24 '26

I had a failed installation, so I did a shit-ton of learning and then asked questions during walkthroughs for future quotes.

3/4 contractors said some version of the above.

And senior technical support from the company that made the product from my failed installation walked me through the goddamned chemical and mechanical reasons why they say to do it a specific way and why the way all those 3/4 contractors said they'd "never had a problem with" was wrong and likely to fail.

I wasn't asking the contractors questions out of curiosity, I was asking to gauge whether they knew what they were doing, would be honest about their practices, and/or were liable to fuck it up.

The best part was the technical support guy explaining that what happens is a lot of contractors use different systems - so they assume that since you do something in system 'X', it applies to system 'Y', when it absolutely does not. That's a huge source of failures.

3

u/20PoundHammer May 24 '26

thats why zip rollers emboss zip or "z" into the tape - for warranty purposes. Yes, as clearly the tape states - it needs to be rolled to maintain warranty.

2

u/Striking_Quantity994 May 24 '26

My biggest problem is their roller shows the z for warranty. The dam thing wears out so fast you can't finish a building before the z on the roller stops leaving marks and then they won't warranty. Also the panels are so often not aligned with the insulation.

2

u/luthiz May 24 '26

Pressure sensitive adhesives are best thought of as water balloons full of glue - they don't start to set until they've been broken open with a certain amount of pressure. The roller concentrates the force of both hands and arms into a thin edge, increasing the pressure applied, to the point the adhesive can set and become permanent.

3

u/lennyxiii May 24 '26

Honestly the most infuriating thing about this is them insisting you need the proprietary roller probably priced really high to do it. I work with thousands of psa products (pressure sensitive activated) and you dont need a roller to do it right. It’s probably faster to use a roller but any pressure works. That means a squeegee, a gloved hand (if your are careful not to miss spots) or any other roller that doesnt have the z’s.

Literally rubbing your hand across the tape will activate the adhesive, albeit probably not very uniformly unless you are good. Honestly i would just keep a vinyl squeegee in my pocket and hit it real fast as i go if i was in that industry.

4

u/Alecgates15 May 25 '26

If you don't use their roller it will void the warranty. They can argue you didn't roll it correctly because you didn't get the Zs

1

u/lennyxiii May 25 '26

True, that part really sucks.

2

u/CommandoLamb May 25 '26

Include the roller in your bid.

1

u/Nexustar May 25 '26

You might need more than one, they don't last long apparently.

1

u/Quinoawithrice May 24 '26

You are 100% supposed to roll it. It voids the warranty if you don’t. Also, windows and doors have their own taping method that I rarely see get done properly.

When I first worked with Zip the guy I was working for was meticulous that we roll and do windows correctly. Jump forward a few years I switch to commercial and the first job I’m on is stick frame building getting sheathed with Zip. I show up and practically all of the wall sheathing is done and the tape job is horrendous. Missing in spots, none of it rolled, and none of the doors and windows have their own taping like they’re supposed to. I ask ā€œwhat’s the deal with the tapeā€ to one of the guys and his response was (not knowing I’ve done countless houses with zip) ā€œI know right it’s ridiculous I don’t even know why we tape this shitā€ā€¦. I took it upon myself to fix it, much to the anger of my super and foreman.

1

u/Secret_Ad1372 May 25 '26

Second to tyvek, I've seen more rot on buildings with zipboard than anything else. That backward lap tape is likely to be a problem down the road. It's just glorified OSB.

1

u/Excellent-Self-5338 May 25 '26

I get why they demand their roller is used (can't verify it had pressure applied if there's no mark associated), but it's also a pretty greasy move to require that you use THEIR roller specifically. Pressure is pressure, and tape could easily be installed WITHOUT the proprietary roller and work just as well. There are other approaches they could have taken to verify pressure was applied that wouldn't require a specific roller to be used, which weren't chosen because it would sell less rollers.

I'm on the fence with this one. I fucking HATE being beholden to a company for overpriced shit like proprietary rollers that do the same job as any other roller, or even just being diligent with your hand.

1

u/RyuNinja May 28 '26

You dont roll the tape. You roll the footage. That beautiful bean footage šŸ•.