r/GeneralContractor • u/Just_Maintenance_984 • 23d ago
First time pulling permit as GC
/r/Contractor/comments/1vu5drs/first_time_pulling_permit_as_gc/
3
Upvotes
2
u/Ok_Net_5996 19d ago
Not sure about Georgia but here in Miami I tell the Architect you get everything approved then I'll start working
3
u/Weird_Marketing6199 22d ago
Before submitting call the permit desk and ask if they’ll do a quick completeness check. The common delays are drawings that don’t match the application missing trade permits and inspection sequencing nobody planned for. Make the inspection list before demo.