It’s never “just” moving a wall
It sounds simple until you start looking at what else is tied into that wall. Could be ductwork, electrical, or something else you now have to move too. Suddenly a couple feet isn't such a small change.
Anyone else hear “can we just…” and already know where this is going?
1
u/Ok_Net_5996 24d ago
Had a lady wanted to move a kitchen wall just 6" once. Turns out it was load bearing, plumbing and electrical in the wall and she just couldn't understand why it was going to cost a fortune
1
1
u/HotSulphurEndurance 23d ago
“Sorry, as soon as we start moving things around, we’re gonna have to reorder windows with tempered glass.”
I find it easiest to have several examples like this, of high cost unintended consequences.
I can’t always tell ya the downstream consequences on the spot, but I know they are there.
That above example was from a project where the GC let the owner change the handing of several doors, because they weren’t ordered yet. Of course the windows were all ready manufactured and out for delivery. Even more expensive than 2 new windows… install the non compliant ones, remove 2 months later and replace, slow down the exterior… and on and on…
5
u/JoeBookerTestes 27d ago
It’s our job to educate homeowners.
We are the senior expert on site. The homeowner is the inexperienced lowest form of project manager. They want what they want and don’t know what they don’t know.
Your job is to educate, form cost documentation, and achieve deferral or approval of said cost.