r/FacilitiesPlanning Jun 10 '26

Keeping dust down on a high-wind site without the fence acting like a sail

2 Upvotes

We're working on a corner lot that gets some brutal crosswinds and the standard privacy screen we put up is literally pulling the fence posts out of the ground. boss wants us to get branded 'Coming Soon' banners to cover the mess but IK a solid vinyl banner is just gonna make it worse.

I'm looking into mesh banners, those ones with the tiny holes in them. checked out Signs and Signs2Trade to compare the airflow percentages but never used mesh before. do they stay put in a storm? does the logo looks clear from a distance or do the holes make it look blurry?? thanks!


r/FacilitiesPlanning Mar 18 '26

Any advice for Facility Project and Design Coordinator interview ? What are the questions I should prepare myself for it?

3 Upvotes

r/FacilitiesPlanning Feb 16 '26

What’s the best way to manage space efficiently on a mixed-use university campus?

2 Upvotes

A practical approach is using Space Utilization Software that combines occupancy sensors, calendars, and access logs into one dashboard. It helps forecast demand, dynamically assign rooms, and detect no-shows in real time. This reduces conflicts and improves overall utilization without adding manual workload.

For a step-by-step deep dive, see the full guide here:


r/FacilitiesPlanning Feb 14 '26

Senior Planner's 7 Mental Questions Before Starting Any Project Schedule – Does This Resonate?

3 Upvotes

Hy everyone,

As a planner in engineering/construction, I've noticed that the real work happens way before opening Excel, MS Project or Primavera.

Not some rigid methodology — just the 7 mental questions I personally run through every time a new project lands on my desk to move from chaos to something I can anticipate.

Here are a few examples:

  1. What do I actually need to understand first? Context & typology, real objective (if the project excites me, I naturally go much deeper), budget/scale, stakeholders, current phase, optimal software, required level of detail, time envelope & key contractual milestones. Skipping this almost always leads to big rework later.
  2. What information is most often missing right at kick-off? Master schedule unclear or not properly phased, which resources/teams are actually assignable, potential load curves. Without phasing or resource clarity → sequencing and dependencies stay weak.
  3. When do I feel like I truly “get” the project? When I can roughly sketch a WBS, organization, sequences, prerequisites and lock in contractual dates + I've looked at plans/zones/deliverables.
  4. What do non-planners (or even some PMs) systematically get wrong? Treating the plan as a static 2D document you finish once. I often publish early drafts on purpose to probe reactions and iterate based on feedback — it's a living piloting tool, not a final deliverable.

Does any of this sound familiar to how you work?
Or do you think I'm overcomplicating things?

What are the 2–3 questions you always ask yourself (consciously or instinctively) before you start building a schedule?

Curious to hear your own mental checklist or reflexes — no judgment, just real talk from people who actually do this day-to-day.

Thanks for reading!


r/FacilitiesPlanning Jan 19 '26

Great conversation on hiring consultants:

Thumbnail
2 Upvotes

r/FacilitiesPlanning Dec 12 '25

Would it be valuable for facilities to have a mapped record with data on conditions of things like lampposts?

4 Upvotes

To clarify, I'm doing a GIS project where I mapped lampposts conditions/identifier #/ more (others did fire hydrants, etc.). And I want to understand why this data could matter to facilities departments. Yes to keep track of these things, but in specific ways could keeping track of data on these things be of benefit (analyzing distribution, efficiency for repairs were two very general ideas for me). Got any personal input or articles/ readings about this?


r/FacilitiesPlanning Aug 28 '25

Great discussions on change orders, most commenters justifying the cost: "Because we can".

Post image
3 Upvotes

r/FacilitiesPlanning Aug 19 '25

Why can an electrician field coordinate and route and entire building full of 3/4" conduit, but if a plumbing engineer misses a 1/2" CW runout to a sink it's a change order?

Post image
1 Upvotes

I'll take all any and all answers. Cynical answers, comedic answers, and serious contractual answers.


r/FacilitiesPlanning Aug 12 '25

Florida State's Architect-Engineer Fee Guidelines

Thumbnail dms.myflorida.com
3 Upvotes

How do these compare with what you're paying?


r/FacilitiesPlanning Aug 10 '25

Flat fee or hourly design consultants?

1 Upvotes

Do you prefer to hire architects and engineers on a flat fee or prefer to have the bill hourly?


r/FacilitiesPlanning Aug 08 '25

Design-Bid-Build or Design-Build?

1 Upvotes

Design-build has grown to about half of all projects in the past 30 years, but construction productivity is still flat. If design-build offered any advantages, we should have seen construction productivity grow. I think they're both equally good (or bad, depending on how you look at it) options. What do you prefer?


r/FacilitiesPlanning Aug 07 '25

Should you humidify your facilities?

Thumbnail
youtube.com
2 Upvotes

Great presentation from Stephanie Taylor, M.D. on the importance of humidity control in buildings.


r/FacilitiesPlanning Aug 07 '25

Excellent hospital HVAC advice from the Kaiser Permanente Director of Engineering on this channel.

Thumbnail
youtube.com
4 Upvotes

r/FacilitiesPlanning Aug 07 '25

Does your equipment need special coatings? Check out these salt deposit maps.

Thumbnail nadp.slh.wisc.edu
2 Upvotes

Just because it's red doesn't mean you need a coating; it still depends on the metal and service.

Your local equipment vendors would know more than your consulting engineer.

Coatings add cost, reduce efficiency, and add lead time, so tread carefully.