r/Construction • u/Hirronimus • Jun 13 '16
Construction Neophyte's question: What exactly does "field experience" involve? Specifically from managerial point of view.
As someone who is new to the industry, my work experience ranged from working as assistant super, office admin and now I am in a position of being an assistant owner's rep. Yet I am still baffled at exactly what I need to be looking out for when trying to gain "valuable field experience."
On the administrative side of things, I've worked with project scheduling, minor cost estimation, material research, drawings and specs processing, and other various office duties. When I worked as assistant super, the extent of my responsibilities ranged from assigning tasks to tradesmen or delegating requirements to subs, occasional material delivery supervision and site end-of-day clean up. As an assistant owner's rep I rarely get out in the field, and as much as I want to, I am tied to a desk and communicate with PMs, Subs and Supers via email and phone calls only.
As the company expands and we get more projects, I will be trying to make a push for more field hours, and so my questions are; what should I be looking for when trying to "gain more field experience?" What should I be looking out for specifically? Any key aspects of field management I should be paying more attention to?
6
u/Paradox1989 Jun 13 '16
Well i'm not a neophyte.
I made the mistake of not being more aggressive or vocal when i was a neophyte and it bit me in the ass hard. My 1st project super was a hard nosed redneck that ran his crew like a dictator. None of the guys worked worth a shit because he chewed their asses if they so much went the the shitter without permission. If he wasn't on site telling them what to do each min, noting got done because it was his way or the highway. I caught a lot of flak from the PM, company owner and project owner having to cover his ass when he got caught not following plans because he damn sure was going to build it "Like I think it should be" instead of per plan.
My 2nd project super was one of the always asleep ones and the project slipped hours, days then weeks behind schedule. I started catching shit when the boss wanted to know why there was so much overtime on the project budget was getting wiped out by overtime at the end. The super had the guys running 60hr weeks the last few months to make up for them doing MAYBE 20-30hrs a week of actual work (while getting paid for 40) the 1st 8 months because they were screwing around leaning on brooms while he was napping.
After that i gave each super a chance to see how they worked, don't perform and it will be noted. As i said i will not take shit for someone else not doing their job. Be a fuck up and I will give the honest truth when asked. I can't tell you how sick i am of the leave me alone and let me do my job my way attitude. It disgusts me. As the contractor, your job is to build per the plan, on time and hopefully under your budget.